Twelve fictional beach bars in Mallorca need ice; two depots and six trucks supply it.
Heat, weekends and surprise parties drive demand, while stored ice melts.
Selling out hides demand: an empty freezer records no sales, even when people still want drinks.
This project reconstructs that missing demand, forecasts uncertainty and plans constrained deliveries.
It replays the same summer under different ordering rules to measure cost, service and waste.
The result: the simple seasonal P95 ordering rule costs €103,405 and serves 96.2% of demand, beating the optimizer in this fixed-seed experiment. The hoped-for case where the most accurate forecaster produces worse decisions did not occur. The project reports that honestly, alongside the limits of the experiment.
Open the interactive 2D / 3D replay
Choose a policy, select a bar and scrub or play through the season. All charts follow the selected day. No installation or login is needed to explore the published replay.
- 3D island: ice columns at each bar, capacity outlines and animated deliveries. Teal trucks travel out with ice; purple trucks return empty to their depot.
- 2D analysis: compare forecasts with demand and sales, and follow deliveries, closing stock, melting, depot dispatches and ice in transit.
- Customers: count bars receiving deliveries, plus clearly labeled visitor equivalents estimated from bags. These are illustrative estimates, not people tracked.
Efficiency charts show service, truck loading, fleet use, production use, ice yield and cost per sold bag. Palma and Alcúdia have daily production limits; the simulator does not model stored depot inventory. Unused production capacity is labeled accordingly. Routes and return animations illustrate saved shipments; they are not GPS or road traces.
The replay also works offline: download docs/index.html using GitHub's Download raw file button and open it in a browser.
- Simulate a summer. Seeded weather, tourism, weekdays and random events create demand, including three bars with intermittent sales. Keep the true demand for evaluation, but give the forecasting models only censored sales and observable stockouts.
- Reconstruct and forecast. Estimate missing demand from earlier similar days. Compare a seasonal baseline with a gradient-boosted hurdle model, which explicitly handles zero-demand days. Both predict P10, P50, P90 and P95 demand quantiles.
- Choose deliveries. Compare last-week averages, median forecasts, a service-target quantile and a SCIP mixed-integer optimizer. Every policy obeys storage, case-pack, minimum-order, production, truck, cut-off and lead-time constraints.
- Replay decisions. Retrain weekly on each policy's own observed history and replay the same demand day by day. Count stockouts, melting, trips and total cost.
The challenge is balancing an empty freezer against an expensive puddle. Forecast accuracy is measured separately from the quality of the resulting decisions.
Seed 20261008, May–September 2025: 49 warmup days and 104 evaluated days. The target is 95% fill rate, defined as bags sold divided by bags demanded.
| Policy / forecaster | Total cost | Fill rate | Lost bags | Melted bags | Trips |
|---|---|---|---|---|---|
| Last-week average | €642,706 | 56.7% | 51,163 | 627 | 762 |
| P50 / seasonal | €288,232 | 82.3% | 20,941 | 1,181 | 956 |
| P95 / seasonal | €103,405 | 96.2% | 4,532 | 6,376 | 1,022 |
| Optimizer / seasonal | €105,271 | 96.1% | 4,646 | 7,131 | 1,025 |
| P50 / hurdle | €336,082 | 78.9% | 24,923 | 1,026 | 968 |
| P95 / hurdle | €111,130 | 95.6% | 5,237 | 6,272 | 1,060 |
| Optimizer / hurdle | €105,553 | 96.1% | 4,660 | 7,301 | 1,034 |
Cost includes transport, holding, melting and a lost-sales penalty; it is not full business accounting. Service is measured across all bags, not guaranteed for each bar or day. Low melting in the naive policy mostly means there was too little ice.
The seasonal forecaster has slightly lower one-day MAE (34.00 versus 34.22 bags) and slightly lower optimizer cost. That €282 difference is small, especially with a 1% solver gap tolerance. No seed search was used to manufacture a ranking. The optimizer plans only today's orders over four days with nine demand scenarios; its approximations help explain why it need not beat a simple rule in replay. See the methodology and result audit for calibration, reconstruction limitations and the full accounting assumptions.
With Docker and Compose:
docker compose run --build --rm ice-networkOr with Python 3.11 and Make:
make setup
make run
make test lintOpen artifacts/replay.html in a browser. The run also writes plots, policy
results, forecast scores, daily ledgers and solver diagnostics to artifacts/.
Allow a few minutes. No API keys, external datasets or commercial solver license
are needed. The first install needs internet access; the replay does not.
The Docker image and Python dependencies are pinned. Docker uses Linux amd64, tested locally; ARM machines use Docker's emulation.
make simulate # Only generate demand, observations and simulator plots
make visualize # Rebuild the replay from an existing completed backtest
make demo # Also refresh the committed docs/index.html snapshot
# Try a different seed and service target without replacing published results:
.venv/bin/ice-network run --seed 42 --service 0.90 --output artifacts/alternativeModule under src/ice_network/ |
Responsibility |
|---|---|
world.py, demand.py |
Mallorca locations, constraints and seeded demand |
simulator.py |
Inventory, melting, pipeline, censoring and ice conservation |
forecast.py |
Past-only reconstruction and probabilistic forecasts |
optimize.py, policies.py |
Scenario MILP and simpler ordering rules |
backtest.py |
Rolling replay and separate forecast/decision evaluation |
plots.py, cli.py |
Figures and command-line entry points |
visualize.py, web/ |
Offline replay, 2D charts and Three.js scene |
Sixteen Python tests cover censoring, conservation, forecast leakage, MILP feasibility, timing and replay accounting. Ruff checks formatting and lint. Optional browser checks cover controls, offline use, mobile layouts and 2D fallback; instructions are in the validation notes.
Start with real sales, availability and stockout timestamps, issued weather forecasts and road travel times. Model uncertain lead times and demand shared across bars, then add multi-echelon depot inventory and future replenishment decisions. Give operators overrides, exception handling for late trucks or broken freezers, and audit logs. Test multiple seasons and cost assumptions before trusting small rankings.